项目动态:菲律宾大跨度物流仓库交付使用Project Update: Wide-Span Logistics Warehouse Delivered in the Philippines

项目动态 · Projects Xionglan Engineering Team

36m 无柱空间 + 台风区抗风设计,从合同签订到移交使用共 132 天。A 36m column-free interior with typhoon-zone wind design — 132 days from contract to handover.

位于吕宋岛的物流仓库项目交付使用:建筑面积 12,000㎡,主跨 36m 无柱空间,边跨设两层办公夹层。

项目地处台风走廊,设计基本风压按当地 50 年一遇取值,屋面采用 360° 直立锁边系统,檐口与屋脊区域檩条加密、抗风连接件按计算配置;结构同时按当地规范做了地震工况验算。

现场安装由当地施工队完成,雄岚派驻两名工程师指导,主体安装 41 天。加上海运与清关,从合同签订到移交使用共 132 天——这是钢构方案在工期上的直接答案。

This logistics warehouse on Luzon island has been handed over: 12,000 m², a 36m column-free main span, and a two-story office mezzanine in the side span.

Sited in a typhoon corridor, the design uses the local 50-year wind pressure, a 360° standing-seam roof, densified purlins and calculated wind connectors at eaves and ridge, plus seismic verification under the local code.

Erection was done by a local crew guided by two Xionglan engineers — main structure up in 41 days. Adding shipping and customs, contract to handover took 132 days in total: steel's answer to schedule, in numbers.