项目动态:大型商业卖场钢结构完工交付Project Update: Steelwork Completed for Large Retail Mall

项目动态 · Projects Xionglan Engineering Team

总建筑面积 21,000㎡,二层大跨卖场 + 三层停车平台,从开工到主体完工仅用 97 天。21,000 m² of two-level retail space plus a parking deck — main structure completed in just 97 days.

本项目为两层的商业卖场建筑,总建筑面积约 21,000㎡,采用钢框架 + 楼承板组合楼面体系,底层柱距 9m,卖场区实现 24m 无柱大空间。

项目难点在于工期:业主要求赶在销售旺季前开业。我们把构件拆分设计做到最细,现场全部螺栓连接、无动火作业,主体结构从进场到封顶仅用 97 天,比传统方案节省约 60 天。

目前内装与机电已进场施工。这再一次验证了钢构在商业建筑上的工期优势:开业时间,就是真金白银。

This two-level retail building covers about 21,000 m², using a steel frame with composite floor decking: 9m column grid at ground level and a 24m column-free sales hall.

The challenge was schedule — the owner required opening before the peak shopping season. With highly detailed member breakdown and an all-bolted, hot-work-free site process, the main structure was topped out 97 days after mobilization, roughly 60 days faster than a conventional scheme.

Interior and MEP works are now underway. It proves once again that in retail, schedule is money.